Hamworthy Park improvements 2017-18

Last updated 4th April 2018

The Project

In partnership with the Friends of Hamworthy Park:

  • New fitness area official opening event postponed … unfortunately the weather has beaten us again and the Beats and Bars event scheduled for Saturday 7th April at Hamworthy Park is postponed. The park is waterlogged and more rain is forecast. We will be rescheduling this event and look forward to the sun (eventually) making an appearance!
  • Completed March 2018 – improved on-site signage has been installed, with old signs replaced and new signs introduced at Branksea Avenue and pedestrian bridge link
  • Completed October 2017 – new footpaths creating a tarmac link from the pedestrian bridge to the promenade (60 linear metres in total), and introducing new landscape schemes, specifically at the pedestrian Lulworth Avenue pedestrian entrance and Branksea Avenue entrance

Still to come:

  • Natural Play – introducing natural play within the eastern end of the park alongside a new natural maintenance scheme.

Photo Galleries

New & improved park signage

Improved fitness area for older children

Footpaths & Landscaping

Hamworthy Park

Lulworth Avenue
Hamworthy
Poole BH15 4DH

Project details

Budget £81,752
Funding Planning Obligations (Developer Contributions)
Project Leader Karl Stokes
T. 01202 261700
E. environment@poole.gov.uk

In partnership with

Friends of Hamworthy Park

The Friends of Hamworthy Park

Join us on Facebook

Keep up-to-date

Parks & open spaces Newsletter; please click below to subscribe to a regular copy

Parks and open spaces Newsletter sign-up

Share This